Smart Hands & Remote Hands

Cross-Connects.

End-to-end management of data center cross-connect provisioning, from order coordination through physical installation and connectivity testing.

Overview

What is Cross-Connects?

Cross-connect services handle the ordering, installation, and testing of physical cross-connects within colocation and carrier-neutral data centers. We coordinate with the facility provider, specify the correct cable type and connector, supervise or perform the installation, and verify end-to-end connectivity using optical or copper testing equipment.

WHY IT MATTERS

Why Cross-Connects matters.

A cross-connect is a short piece of cable with a long list of dependencies. The facility needs a correct order, the other party needs to authorize the link, the media must match the optics at both ends, and someone has to confirm that light or signal actually arrives. Mistakes in this chain are common and slow to surface: a mismatched fiber type, a swapped transmit and receive pair, or a patch to the wrong port can leave a new circuit dark while each party blames the other. Having one coordinator who tracks the order and checks the result shortens that argument.

Done well, the link is ordered with exact port identifiers on both ends, delivered by the facility, then tested before anyone declares it ready. Measured light levels are written down, connectors are inspected and cleaned if needed, and both ends carry labels that match your records. The documentation matters as much as the cable, because the next engineer to troubleshoot this link will rely on it. You end up with a circuit that works on day one and a file that explains how it was built.

SCOPE

Scope of service.

  • 01Cross-connect order submission to the facility provider
  • 02Cable type and connector specification (single-mode, multi-mode, copper)
  • 03Installation supervision or direct installation by our engineers
  • 04Optical power level testing and documentation
  • 05Copper continuity and performance testing
  • 06Labelling and documentation at both ends of the cross-connect

CHOOSING

Choosing this service.

What to decide before you order, and what sits outside the scope.

Order management or install only

Some customers place the order themselves and only need verification when the facility finishes. Others want us to prepare the paperwork, track the facility and chase the other party. Decide which you want, since facility rules about who may place an order differ between sites.

Match the media to your optics

Fiber type, connector style and polarity must agree with the transceivers on both ends, and copper links have their own limits. Confirm optics and distances before ordering, because a wrong choice means a second order, a second round of fees from the facility and a delay to the circuit.

One link or a batch

A single link is straightforward. A batch, such as a group of links to a cloud on-ramp, benefits from a numbered plan that maps each link to ports and labels. Planning the batch as one piece of work helps prevent duplicated or crossed paths and keeps the records consistent.

Know who authorizes the link

Carriers, cloud providers and neighbors in the same facility each have their own process for approving a connection. Find out early who must supply authorization paperwork and how long that party typically takes, since that approval step often controls the whole schedule and cannot be rushed from our side.

Not included

  • Monthly cross-connect fees and one-time installation charges are billed by the facility to you, not by Deploris.
  • Carrier circuit ordering, bandwidth contracts and provisioning on the carrier side remain between you and the carrier.
  • Router or switch configuration, optics purchasing and interface bring-up are outside this service unless scoped separately.
  • Cabling that runs beyond the facility, such as between buildings or campuses, is a separate cabling project.

USE CASES

Typical scenarios.

Scenario 01

A company ordering a new Internet circuit at its colo and needing the cross-connect installed and tested to its router rack.

Scenario 02

A cloud migration requiring 10 new fiber cross-connects between the customer's cage and a cloud provider's on-ramp.

Scenario 03

A network engineer troubleshooting a degraded circuit and needing someone to clean and re-seat the fiber connectors at the meet-me room.

PROCESS

How the work runs.

  1. 1

    Confirm endpoints and media

    We collect port identifiers, optics type, connector style and the authorization details for both ends, and check that they agree. Gaps are raised with you before an order is submitted.

  2. 2

    Place and track the order

    The order goes to the facility with the confirmed details, and we follow it through to completion. Status updates come to you, and any question from the facility is answered promptly, without waiting for your team to return to the desk.

  3. 3

    Inspect and test the link

    When the facility reports the cable in place, our engineer inspects connectors, cleans them if needed and measures the link with suitable test equipment. Readings are noted against the expected range.

  4. 4

    Label and document

    Both ends are labeled to your convention, and the circuit record is updated with port details, media, test readings and photos. You receive the file for your asset system.

FAQ

Frequently asked questions.

What types of cross-connects do you support?
We support single-mode fiber (LC, SC), multi-mode fiber (OM3, OM4), and copper (Cat6, Cat6a) cross-connects. We specify the correct type based on your equipment and circuit requirements.
How long does a cross-connect installation take?
Once the facility provider has run the cable (typically three to five business days from order), our engineer verifies and tests it within one to two hours.
Do you coordinate with carriers and ISPs?
Yes. We liaise with carriers, ISPs, and the facility's meet-me room team to ensure the cross-connect is correctly patched to the right demarcation point.
Can you test an existing cross-connect that seems faulty?
Yes. We test optical power levels, inspect connector cleanliness, and verify end-to-end connectivity to isolate the fault.
What information do we need to provide before ordering?
Provide the facility name, cage or suite, the exact port or panel at each end, the media and connector type, and the other party's authorization details. If you are unsure of any item, tell us. We would rather ask before ordering than have the facility install something that does not fit.
What if the light levels look wrong after installation?
The engineer first inspects and cleans the connectors, since dirt is a frequent cause, then retests and checks polarity. If the reading is still outside the expected range, the finding goes to you and the facility with measurements attached, so the right party can correct their side.
Can you help where only the facility's technicians may run cabling?
Yes. Many facilities restrict installation to their own staff. In that case we prepare and track the order, meet the result at your equipment, then test, label and document the link. The cable is theirs to run, while verification, labeling and the written records remain our part of the job.

QUOTE

Request a quote.

Share a few details and we will come back with the next steps.

Get started

Need engineers on site? Tell us where.

Tell us the sites, the scope and the timeline. We reply with a written plan.

Go to

Saved and recent pages stay on this device. Press ? for keyboard shortcuts.

Keyboard shortcuts

Search the site
/ or Ctrl K
Show this list
?
Switch light, dark or system theme
t
Save or unsave this page
s
Go to the home page
g then h
Go to services
g then s
Go to coverage
g then c
Go to the contact form
g then q

Shortcuts are off while you type in a field.